Synchrotron Construction Timeline

2001

Australian Synchrotron Project funding announced by the Victorian Government

2002

Formation of scientific and machine advisory committees
Site launch and preparation

2003

Machine design announced
Building and associated facilities contract awarded
Construction started
Injection system contract awarded

2004

All particle accelerator systems contracts awarded
Beamline design process starts
Formation of industry advisory committee

2005

Building complete
Machine assembly starts

2006

Installation and commissioning of machine and beamlines begins
Selection of operator

2007

Commissioning of first beamlines complete
31 July: Australian Synchrotron formal opening

More information

Images:
Building construction
Machine installation and commissioning